What construction finance costs developers in Australia

Ventas Asset Lending  |  Reviewed by Caleb Morehu  |  Updated 31 October 2026

Non-bank construction debt is published from 9.99% a year (La Trobe), and guides put it at 8% to 11.95%, plus 1% to 3% establishment. Our arithmetic for six townhouses costing $3.2m over 18 months is $189,000 to $304,000 of finance cost, with peak debt near $2.2m. Banks price lower but want presales.

From 9.99%a year, La Trobe development loan, variable, interest only, up to 3 years
Up to 70%of end value, the published maximum at La Trobe and Assetline
0% to 50%presales at non-banks, against 70% to 100% of debt at banks (Feasly)
$189k to $304kfinance cost on a $3.2m, six townhouse project over 18 months (our arithmetic)

Developer finance is priced by risk, not by a rate card. A bank can lend at a few points above the cash rate if you bring presales and a big slice of equity, while a non-bank or private lender will fund the same site faster with fewer presales and charge several points more. Establishment fees, valuation and quantity surveyor costs and capitalised interest sit on top. This guide sets out what lenders publish, the bands guides report for each lender type, the gearing and presale limits, and the full finance bill on a six townhouse project.

What lenders publish for construction and development finance

Most developer finance is priced by phone, so few rates are public. The table sets out what three lenders show on their own pages on 30 October 2026. Figures are the lender's, indicative market data and not Ventas offers. Where a page gives no figure the table says Not disclosed. Innovate Funding is a private lender and its page covers bridging around a build, not the build loan itself, but it is the only private lender we found that publishes rates.

Lender pageProject sizeRate shownFees shownMaximum gearingTerm and interest
La Trobe Financial, development loan$100,000 to $50,000,000, multi-dwelling or commercialFrom 9.99% a year variable, set by loan size and risk gradeApplication fee from 1.50%, valuation and legal extra70% LVR up to $5m, 65% up to $50m, never above 80% of total development costUp to 3 years, interest only, residential or commercial security
Assetline Capital, construction$1m to $3m, 1 to 2 dwellingsNot disclosed (price on application)Not disclosedUp to 70% of end valueUp to 24 months, interest capitalised, no repayments
Assetline Capital, development$3m to $40m, townhouses, apartments, mixed use, commercialNot disclosed (price on application)Not disclosedUp to 70% of end valueUp to 36 months, progressive drawdowns, presales assessed against project and sponsor with no figure given
Innovate Funding, first mortgage bridge around a build$250,000 to $20m or moreFrom about 8.95% a year, up to 11%Establishment 1% to 3%, default rate 4% to 6% above the standard rateAbout 75% of current value or 65% of end value, FAQ says 65% to 70% of current value1 to 12 months, occasionally 18, interest prepaid or capitalised
Innovate Funding, second mortgage bridge$250,000 to $20m or more12% to 16% a yearEstablishment 1% to 3%Combined LVR usually 70% to 75%1 to 12 months, sits behind the first lender

None of the four major banks publishes a development finance rate or presale hurdle that we could find. Bank figures in this guide come from a development feasibility publisher, Feasly, which says its numbers are indicative and should be checked against a current term sheet. Its pages were last updated on 7 August 2026. The Reserve Bank lifted the cash rate to 4.60% on 30 September 2026, up from 4.35%, so anything priced before then may have moved.

This guide is about business-purpose and developer construction finance. A loan to build your own home is consumer credit and is not covered here.

Rates by lender type and project size

The same publisher sets out what each class of lender charges and asks for. Read them as bands, not quotes. Banks are cheapest and slowest, and want the most presales and equity. Non-banks charge more, move in weeks and accept far fewer presales. Private lenders and mezzanine fill the gaps at a higher price.

Lender typeRate a yearEstablishment and other feesGearingPresalesApproval time
Major bank, senior construction5.00% to 7.50% on one guide, 5.5% to 7.5% on another1% to 2% establishment, line fee on undrawn limit not uncommon60% to 70% of cost, 60% to 65% of end value70% to 100% of debt on one guide, 100% to 120% cover on another8 to 12 weeks
Institutional non-bank, senior8.5% to 11.5%1% to 3% establishment, line fee often nil, interest on drawn balance only70% to 80% of cost, 65% to 70% of end value, up to 75%0% to 50%4 to 6 weeks
Mid-market non-bank, senior9.5% to 13.0%1% to 3% establishment70% to 80% of cost, 65% to 70% of end value0% to 50%4 to 6 weeks
Shorter-term private senior10.75% to 14.0%, 16% or more on another pageUp to 3% establishment, exit fee nil to about 1%75% to 90% of cost or value depending on the pageMinimal or nil1 to 4 weeks
Mezzanine behind senior debt14% to 22%, plus 2% to 5% of project profit2% to 4% establishment, minimum interest period 9 to 12 months10% to 20% of cost on top of seniorNot applicableNot published

Project size changes who is interested and how the file is tested.

Project sizeTypical facilityWhat is publishedWhat changes
Duplex and townhouses, 1 to 6 dwellingsAbout $1m to $5mAssetline: up to 70% of end value on $1m to $3m, interest capitalised. La Trobe: 70% LVR up to $5mBank loans above roughly $1m to $2m commonly need a quantity surveyor report at each draw (Feasly). Non-banks fund with 0% to 50% presales
Mid-size residential, 7 or more dwellingsAbout $5m to $40mAssetline: $3m to $40m up to 70% of end value. La Trobe: 65% LVR above $5mBanks ask for presales and 30% to 40% cost equity. Mezzanine fills the gap between senior debt and your cash
Commercial, industrial and mixed useAbout $3m to $50mLa Trobe lends on commercial security. Assetline lists commercial under development finance. No rates publishedBanks look for pre-lease commitments of 50% to 80% of lettable area (Feasly). Non-banks assess the exit

Lenders also size to the lower of two tests. Loan to cost (LTC) compares the facility to total development cost. Loan to value (LVR) compares it to the expected end value. One guide says many lenders look for 20% to 35% of total development cost as equity, so your cash is usually the binding limit, and that lenders may discount end value by 10% to 20% when they test it.

Presales: what banks ask for and what changed in 2025 and 2026

Banks commonly want qualifying presales of 70%% to 100%% of the debt, and one guide puts the current norm at 100%% to 120%% cover. That habit traces to a 2017 APRA letter that described lenders asking for presales of at least 100%% of committed debt. On 13 February 2025 APRA wrote that this was industry practice and did not represent a minimum requirement or expectation of APRA, and that it had not set minimum presale requirements in its standards.

A proposal is now on the table. On 29 June 2026 APRA consulted on halving the qualifying presale threshold for the lower risk weight on residential development lending from 100%% to 50%% of total debt, with a proposed start of 1 April 2027. It is a consultation, not a rule, so bank policy has not changed because of it. Separately, in May 2024 CBA's Business Bank said it would count presale contracts secured through Coposit, up to 10%% of presales, towards its hurdle.

Without presales you are in non-bank territory, which costs more. Our guide to construction finance without presales covers that route, and the deposit for a development loan page covers equity.

Fees on top of the rate, and what 18 months costs

The rate is only part of the bill. Costs that sit on top:

Interest is usually capitalised, which means it is added to the loan and repaid at sale, so there are no repayments during the build. It also means interest is charged on interest, and the facility must be big enough to carry it. Interest accrues only on the drawn balance. Feasly's own example puts the average balance at 55% of the limit over a 15 month build. In our worked project it is about 46%.

The table below prices the finance for six townhouses with a $3.2m total development cost over 18 months (our arithmetic). We assumed the land is bought with your cash, the build is funded by a 70% senior facility drawn monthly, and the rates sit inside the published bands above.

Six townhouses, $3.2m, 18 monthsLow caseMiddle caseHigh case
Senior rate a year, interest capitalised9.0%10.5%12.5%
Establishment fee (1.0%, 1.5%, 2.5% of a $2,240,000 limit)$22,400$33,600$56,000
Valuation, QS, legal and monitoring (our assumption)$30,000$35,000$45,000
Capitalised interest over 18 months$137,000$164,000$203,000
Total cost of finance$189,000$232,000$304,000
Total development cost including finance$3,159,000$3,202,000$3,274,000
Peak debt in month 18$2,199,000$2,242,000$2,314,000
Finance as a share of total development cost6.0%7.2%9.3%

Each extra month at peak debt costs about $19,600 at the middle rate, so a three month delay adds about $59,000 before any default rate or extension fee.

What makes a construction loan fundable

Appetite is real but selective. Construction was the largest industry for company insolvencies in 2025-26 at 3,472 companies, about 24.5%% of the 14,152 total (our arithmetic, from ASIC data reported by Accountants Daily). That is one reason lenders look hard at the builder, not just the margin. Banks will say no to a first time developer without presales and equity. Non-banks will often say yes, at a price, if the numbers hold.

What lenders look for:

Our construction cost per square metre guide sets out the build rates a quantity surveyor will test your budget against.

How the build is funded

A construction project is usually funded in layers. Senior debt comes from a bank, a non-bank or a private lender. Mezzanine debt or preferred equity fills the gap if senior debt plus your cash falls short. Private lending is typically business purpose and not consumer regulated, but that depends on the facts. ASIC says the credit legislation covers loans to natural persons for buying, renovating or improving residential property for investment, while loans to companies are not covered, so lenders will ask who the borrower is and why. Ventas is a finance broker, not a lender, so we do not quote rates here.

Illustrative only, subject to lender assessment. A six townhouse project in the middle case from the table above:

Budget itemAmount
Land, duty and purchase costs$960,000
Construction, six townhouses$1,520,000
Contingency, about 5% of construction$75,000
Design, approvals, contributions and consultants$290,000
Marketing and sales legal$125,000
Finance costs, middle case$232,000
Total development cost$3,202,000

And how it is typically funded across lender types:

Funding layerAmountWhat it coversSecured on
Senior construction facility, non-bank$2,242,000 peak debt, 70% of costConstruction, consultants, marketing and the capitalised finance costFirst mortgage over the site, guarantees, building contract and insurance
Your equity, cash or equity in other property$960,000, 30% of costLand, duty and purchase costs, put in before the first drawdownCash, or a second property if you borrow your equity
Total$3,202,000

The facility limit would be set at $2,250,000 or so, and the expected sale price (our assumption: $4,000,000 excluding GST for six) gives an LVR of about 56% and a return on cost of about 25%, which clears the 15% to 20% guide. A bank would price lower but would want presales on most of the debt. A development finance or construction finance file for this deal starts with the site contract, approved plans, the builder's fixed price contract, a cost plan, your balance sheet and your project history. Tell us whether you can offer presales. Finance is subject to lender assessment and approval.

Sources

This is general information only and not financial, credit, or tax advice. Figures are indicative market data from the sources listed, not Ventas offers, and move with the market. Consider your own circumstances and speak to a professional. All finance is subject to lender assessment and approval.

Frequently asked questions

What interest rate do construction loans for developers charge?

Published and reported non-bank pricing runs from 9.99% a year at La Trobe to about 8% to 13% on guides, and private lenders charge 10.75% to 16% or more. Banks are reported at roughly 5% to 7.5% but publish nothing, and they need presales. Rates move with your file and the lender.

How much of a construction project will a lender fund?

Banks are reported at 60% to 70% of cost, non-banks at 70% to 80%, and La Trobe and Assetline publish up to 70% of end value. Lenders use the lower of the cost and value tests, so most developers need 20% to 35% of total cost as their own equity.

Do I need presales to get construction finance?

Banks commonly ask for presales covering 70% to 100% of the debt. APRA said in February 2025 that it sets no presale minimum. Non-banks often accept 0% to 50%, and some private lenders none, but you pay more. A proposed APRA change would halve the bank capital threshold from 1 April 2027 if finalised.

What fees come on top of the interest rate?

Expect an establishment fee of 1% to 3% of the facility, plus valuation, legal and quantity surveyor costs, and sometimes an exit fee up to about 1%. Interest is usually capitalised, so you also pay interest on interest. A default rate adds 4% to 6%.

Is this the same as a construction loan to build my own home?

No. Building your own home is consumer credit with different lenders, rates and rules. This guide covers business-purpose and developer finance for townhouses, units, commercial projects and builders funding their own projects. Whether a loan is regulated depends on the borrower and the purpose, so check with the lender and a lawyer.

CM
Reviewed by Caleb Morehu, Co-founder, Ventas Asset Lending. Caleb structures asset, property-backed and development finance and negotiates directly with lenders. Every figure on this page is checked against what lenders are actually approving. About Ventas.

Get your number from the lender panel

The figures above are indicative. Tell us what you are buying and we will come back with the real rate and repayment, usually within a day. No upfront fees and no credit check to get a quote.

No upfront fees. We are paid by the lender at settlement.

Your project, priced across lenders

Send us the site, the approved plans and the cost plan. We will show you how banks, non-banks and private lenders would fund the build.

This article is general information only and not financial, credit, or tax advice. Ventas Asset Lending is a finance broker, not a lender. Approvals are subject to lender assessment. Consider your own circumstances and speak to a qualified professional, including your accountant for any tax questions.