What development soft costs run to before you build in Australia

Ventas Asset Lending  |  Reviewed by Caleb Morehu  |  Updated 1 November 2026

Before construction starts, a duplex needs about $48,000 to $157,000 for council fees, design, consultants, reports and quantity surveyor work, and six townhouses about $134,000 to $452,000. That is roughly 2% to 7% of total development cost. The architect and engineers are the biggest lines. The council application fee is the smallest.

$48k to $452kpre-construction soft costs, duplex to six townhouses (our arithmetic)
2% to 7%of total development cost, before contingency, finance and selling
$9,150Brisbane base DA fee for up to two dwellings, 2026-27
25% to 35%equity a first-time developer is typically asked to contribute

A developer's first cheques go to people who never lay a brick: the council, the architect, the engineers, the planner, the specialist report writers and the quantity surveyor. Those soft costs are paid in cash before a construction lender signs anything, and they are easy to leave out of an early feasibility. This guide prices each line from published fee schedules and guide ranges, applies them to a duplex, a six-townhouse project and a small apartment building, shows them as a share of total development cost, sets out which ones a lender needs before it will move, and explains how the equity and the build are funded.

What the council charges to lodge

The council fee is the smallest soft cost and the only one set by a published schedule. The table applies three 2026-27 schedules to the same three projects. The build costs are our assumption, excluding GST: $1.1 million for a duplex, $3.44 million for six townhouses with site works, and $5.7 million for 12 apartments. For scale, Rider Levett Bucknall's Riders Digest 2026 for Melbourne prices walk-up units at $285,000 to $585,000 a unit and townhouses at $315,000 to $700,000 a unit, current at the fourth quarter of 2025. It states that its build rates exclude land, site works and legal and professional fees, so everything in this guide sits on top of a quantity surveyor's build number.

ProjectBuild cost, ex GSTNSW DA feeVictoria permit feeBrisbane DA fee
Duplex (2 dwellings)$1.1m$3,927$3,980.70$9,150
Six townhouses$3.44m$7,635$3,980.70$10,950
12 apartments, walk-up or low-rise$5.7m$11,215$10,146.10$13,650

How each is built. NSW: for estimated cost including GST between $1 million and $10 million, the 2026/27 schedule is $3,625 plus $1.44 for each $1,000 or part above $1 million (our arithmetic on the assumed costs plus 10% GST). Victoria: Class 13 ($1 million to $5 million) is $3,980.70 and Class 14 ($5 million to $15 million) is $10,146.10, at a 2026-27 fee unit of $17.27. Brisbane: the multiple dwelling fee includes dual occupancy, the base of $9,150 covers up to two units, and each unit from the third to the 70th adds $450 (our reading of the schedule). An impact assessable application adds a further $17,100.

Subdivision is separate. Victoria charges $1,537.00 to subdivide into two lots. Brisbane's reconfiguring a lot fee is $4,500 for up to two lots plus $900 for each lot from the third to the 30th. Infrastructure charges and developer contributions are also separate and usually larger than the application fee, so they are not in this guide; see the townhouse and duplex cost guides. NSW councils also push cost verification onto a quantity surveyor: Bayside Council asks for a QS estimated development cost report on works over $500,000, and a QS gross floor area validation from $3 million.

What the consultants and reports cost

No one publishes an official scale for these fees. Melbourne practice BY Projects Architecture states there is no official architect fee scale in Australia, because the Institute withdrew its guide after competition concerns in 2005, so every number below is a published guide range, not a quote. Feasly's September 2026 guide puts total professional fees at 8% to 15% of construction cost and warns that the published percentages disagree mainly because they use different denominators.

Cost linePublished rangeWhere it appliesSource
Architect or building designerAbout 2% (simple) to 8%+ (complex or heavily documented) of construction costEvery projectFeasly, 22 Sep 2026
Structural, civil and hydraulic engineersAbout 1% to 3% of construction cost each, or as a packageEvery projectFeasly, 22 Sep 2026
Town plannerDuplex: a few thousand to about $5,000. Townhouses and small apartments: $10,000 to $25,000Every projectFeasly, 14 Jun 2026
Traffic and parking assessment$2,000 to $7,000Larger multi-unit projects, set by councilFeasly, 7 Nov 2025
Acoustic report$2,000 to $4,000, or $5,000 to $10,000 if complexBusy roads, apartmentsFeasly, 7 Nov 2025
Stormwater and drainage report$1,500 to $5,000NSW councils such as Bayside want a concept plan on every DAFeasly, 7 Nov 2025
Waste management plan$800 to $2,000Multi-dwelling DAsFeasly, 7 Nov 2025
Arborist report$500 to $2,000Sites with treesFeasly, 7 Nov 2025
Geotechnical investigation$2,000 to $5,000 (basic residential)Required in NSW where there is excavation or a basementFeasly, 7 Nov 2025
QS cost report lodged with the DA$1,000 to $3,000NSW, over $500,000 at BaysideFeasly, 7 Nov 2025
QS feasibility cost estimate$2,000 to $5,000 (residential)Before you buy or commitFeasly, 21 Nov 2025
QS initial report for the lender$3,000 to $10,000, by project sizeBefore fundingIntegrated Finance Group, Aug 2026
QS progress inspection$500 to $1,500 a visitEach drawdown, during the buildFeasly, 21 Nov 2025
NSW Planning Portal fee for a BASIX certificate$5 a certificate, plus the assessor's own feeNSW multi-unit DAsNSW Planning Portal, 2026/27
Energy rating assessor, land survey, lender valuation, lender legalsNot published in the sources we checkedVariesGet written quotes

Ask the architect for a fee that lists the stages it covers. Planning approval is one stage in the middle of a five-stage engagement, and engineers, the quantity surveyor and the land surveyor usually sit outside the architect's fee. Councils decide the report list. Bayside (NSW) asks for a statement of environmental effects, stormwater concept plan, arborist report and BASIX certificate on multi-unit housing, with a design review panel from three storeys. Knox (Victoria) asks for a sustainable design assessment or sustainability management plan, a levels and features plan by a licensed land surveyor, and a Metropolitan Planning Levy certificate with a multi-dwelling permit application.

Soft costs as a share of total development cost

This table adds the lines above for each project: council fee, architect at 2% to 8% of build cost, engineers at 1% to 3%, the planner, the extra reports, and three quantity surveyor jobs (DA cost report, feasibility estimate, lender report). It leaves out contingency, council infrastructure charges, finance, selling costs, land survey, valuation and legals. Total development cost (TDC) is an assumption: $2.5 million for the duplex, $6.2 million for six townhouses and $10.5 million for the apartments, each including land, build, finance and selling costs.

ProjectPre-construction soft costsShare of TDCShare of build costBiggest line
Duplex, TDC $2.5m$48,000 to $157,0001.9% to 6.3%4.4% to 14.3%Architect, $22,000 to $88,000
Six townhouses, TDC $6.2m$134,000 to $452,0002.2% to 7.3%3.9% to 13.1%Architect, $68,800 to $275,200
12 apartments, TDC $10.5m$209,000 to $710,0002.0% to 6.8%3.7% to 12.4%Architect, $114,000 to $456,000

All figures in the table are our arithmetic on published ranges. The spread is wide because the architect percentage is wide, and a signed fee proposal removes most of it. As a cross-check, Feasly's June 2026 four-townhouse example carries $180,000 of professional fees (3.4% of its $5.33 million project cost) and $120,000 of statutory fees and infrastructure contributions. The council fee is a few thousand dollars on the duplex and under 0.2% of TDC on the apartments; the design team is where the money goes. The same costs matter to what an approved site is worth, because a buyer pays for an approval that has already absorbed them, and to subdivision costs, where the approval and survey lines repeat.

What a construction lender needs before it issues terms

A lender does not lend on a sketch. The items below come from two published lender-readiness checklists, so read them as the usual order of events rather than one lender's policy. Lenders differ, and some will give indicative terms earlier than others.

ItemUsually needed before credit approval?What the lender uses it for
Planning permit or DAYes. An issued approval is stronger than a lodged one, and conditions already satisfied reduce risk furtherSets what can be built and the end value
Feasibility with a conservative end valueYesChecks margin on cost, with 18% to 25% cited for a first project
Independent QS cost reportYes. Described as non-negotiable with most lendersCertifies the build cost and sets drawdown amounts
Fixed-price contract with a licensed builderYes. Cost-plus contracts are rarely acceptedFixes the largest cost
Your equity and track recordYes. A first project is asked for 25% to 35% of total project cost as equityShows you can carry a cost overrun
Lender valuation and QS initial reportAfter the lender decides to proceed; the borrower paysTests the end value and the cost to complete

Now the honest part on appetite. Integrated Finance Group's August 2026 guide has a major bank at 65% to 75% of TDC with presales covering 100% of the debt, a non-bank senior lender at 65% to 80% with presales of 30% to 50%, and private or mezzanine money at 75% to 85% combined with presales of 0% to 30%. Feasly's page for the same period gives banks 70% to 80% of TDC and 60% to 70% of end value. Small first projects with no presales and no builder contract struggle at the banks. The soft costs themselves are almost never lent against: you pay them from your own cash before the first drawdown.

How the soft costs and the build are funded

Council fees, consultants and reports are paid before any construction facility exists, so they are equity. Lenders still count them as project cost, which means paying them lifts your contribution toward the 25% to 35% most first-time developers are asked for. The usual way to fund them is cash, or a loan secured on a home or investment property you already own. A development finance facility from a bank, a non-bank lender or a private lender then funds the build against the approval, the QS cost report and the signed contract. Private lending is typically business-purpose and not consumer regulated, and it costs more than bank debt. Ventas is a broker, not a lender, so we do not quote rates here.

Illustrative only, subject to lender assessment. Six townhouses in Brisbane, assumed total development cost of $6.2 million:

Cost lineAmount
Land and acquisition costs (assumed)$1,580,000
Pre-construction soft costs: DA fee $10,950, architect at 4% $137,600, engineers at 1.5% $51,600, planner $15,000, reports $12,000, QS $11,000$238,000
Construction including site works$3,440,000
Contingency at 5% of construction$172,000
Infrastructure charges, utilities, finance, selling and other (balancing figure)$770,000
Total development cost$6,200,000

And how it is typically funded:

Funding layerAmountWhat it coversSecured on
Senior construction facility at 65% of TDC$4,030,000Build and part of the finance, selling and other costsFirst mortgage over the site, assignment of the building contract
Equity in the land$1,580,000Land and acquisitionCash, or a property-backed loan on the land or other property
Soft costs paid in cash$238,000All pre-construction consultants and feesCash or a loan on existing property
Balance of equity before the first draw$352,000Contingency and early costsCash or a loan on existing property
Total$6,200,000

Equity here is $2,170,000, or 35% of TDC. To get a number from Ventas, send the site address, the DA status or lodgement date, your consultant fee proposals, the QS cost estimate or a build quote, your equity sources, and any presale plan. Start at our development application form. Finance is subject to lender assessment and approval.

Sources

This is general information only and not financial, credit, or tax advice. Figures are indicative market data from the sources listed, not Ventas offers, and move with the market. Consider your own circumstances and speak to a professional. All finance is subject to lender assessment and approval.

Frequently asked questions

How much do development soft costs add up to before construction starts?

On our arithmetic from published ranges, about $48,000 to $157,000 for a duplex, $134,000 to $452,000 for six townhouses and $209,000 to $710,000 for 12 apartments. That is roughly 2% to 7% of total development cost, excluding contingency, infrastructure charges, finance and selling costs. Signed fee proposals narrow it.

How much is a DA fee for a townhouse project?

It depends on the state and the build cost. On an assumed $3.44 million build, our arithmetic gives about $7,635 in NSW, $3,980.70 in Victoria and $10,950 in Brisbane under the 2026-27 schedules. Infrastructure charges and contributions are charged separately and are usually larger.

Do I need a quantity surveyor before I apply for a DA?

Sometimes. Some NSW councils, including Bayside, require a QS estimated development cost report on works over $500,000. Lenders also want an independent QS cost report before approval. Outside NSW, councils usually ask for a cost summary, so check your council's lodgement checklist.

Can I borrow to pay the architect and consultants?

Rarely. Consultants and fees are paid before a construction facility exists, so they are normally funded from cash or a loan secured on property you already own. Lenders count them as project cost, so they count toward your equity contribution.

How much equity does a first-time developer need?

One published lender checklist says to expect 25% to 35% of total project cost as equity. Banks lend about 65% to 75% of total development cost and often want presales. Non-bank and private lenders go higher, at a higher price. Each lender sets its own limits.

CM
Reviewed by Caleb Morehu, Co-founder, Ventas Asset Lending. Caleb structures asset, property-backed and development finance and negotiates directly with lenders. Every figure on this page is checked against what lenders are actually approving. About Ventas.

Get your number from the lender panel

The figures above are indicative. Tell us what you are buying and we will come back with the real rate and repayment, usually within a day. No upfront fees and no credit check to get a quote.

No upfront fees. We are paid by the lender at settlement.

Ready for the lender

Send us the site, the DA status and your cost plan. We will tell you what lenders still need and how the project is funded.

This article is general information only and not financial, credit, or tax advice. Ventas Asset Lending is a finance broker, not a lender. Approvals are subject to lender assessment. Consider your own circumstances and speak to a qualified professional, including your accountant for any tax questions.