What development soft costs run to before you build in Australia
Before construction starts, a duplex needs about $48,000 to $157,000 for council fees, design, consultants, reports and quantity surveyor work, and six townhouses about $134,000 to $452,000. That is roughly 2% to 7% of total development cost. The architect and engineers are the biggest lines. The council application fee is the smallest.
A developer's first cheques go to people who never lay a brick: the council, the architect, the engineers, the planner, the specialist report writers and the quantity surveyor. Those soft costs are paid in cash before a construction lender signs anything, and they are easy to leave out of an early feasibility. This guide prices each line from published fee schedules and guide ranges, applies them to a duplex, a six-townhouse project and a small apartment building, shows them as a share of total development cost, sets out which ones a lender needs before it will move, and explains how the equity and the build are funded.
What the council charges to lodge
The council fee is the smallest soft cost and the only one set by a published schedule. The table applies three 2026-27 schedules to the same three projects. The build costs are our assumption, excluding GST: $1.1 million for a duplex, $3.44 million for six townhouses with site works, and $5.7 million for 12 apartments. For scale, Rider Levett Bucknall's Riders Digest 2026 for Melbourne prices walk-up units at $285,000 to $585,000 a unit and townhouses at $315,000 to $700,000 a unit, current at the fourth quarter of 2025. It states that its build rates exclude land, site works and legal and professional fees, so everything in this guide sits on top of a quantity surveyor's build number.
| Project | Build cost, ex GST | NSW DA fee | Victoria permit fee | Brisbane DA fee |
|---|---|---|---|---|
| Duplex (2 dwellings) | $1.1m | $3,927 | $3,980.70 | $9,150 |
| Six townhouses | $3.44m | $7,635 | $3,980.70 | $10,950 |
| 12 apartments, walk-up or low-rise | $5.7m | $11,215 | $10,146.10 | $13,650 |
How each is built. NSW: for estimated cost including GST between $1 million and $10 million, the 2026/27 schedule is $3,625 plus $1.44 for each $1,000 or part above $1 million (our arithmetic on the assumed costs plus 10% GST). Victoria: Class 13 ($1 million to $5 million) is $3,980.70 and Class 14 ($5 million to $15 million) is $10,146.10, at a 2026-27 fee unit of $17.27. Brisbane: the multiple dwelling fee includes dual occupancy, the base of $9,150 covers up to two units, and each unit from the third to the 70th adds $450 (our reading of the schedule). An impact assessable application adds a further $17,100.
Subdivision is separate. Victoria charges $1,537.00 to subdivide into two lots. Brisbane's reconfiguring a lot fee is $4,500 for up to two lots plus $900 for each lot from the third to the 30th. Infrastructure charges and developer contributions are also separate and usually larger than the application fee, so they are not in this guide; see the townhouse and duplex cost guides. NSW councils also push cost verification onto a quantity surveyor: Bayside Council asks for a QS estimated development cost report on works over $500,000, and a QS gross floor area validation from $3 million.
What the consultants and reports cost
No one publishes an official scale for these fees. Melbourne practice BY Projects Architecture states there is no official architect fee scale in Australia, because the Institute withdrew its guide after competition concerns in 2005, so every number below is a published guide range, not a quote. Feasly's September 2026 guide puts total professional fees at 8% to 15% of construction cost and warns that the published percentages disagree mainly because they use different denominators.
| Cost line | Published range | Where it applies | Source |
|---|---|---|---|
| Architect or building designer | About 2% (simple) to 8%+ (complex or heavily documented) of construction cost | Every project | Feasly, 22 Sep 2026 |
| Structural, civil and hydraulic engineers | About 1% to 3% of construction cost each, or as a package | Every project | Feasly, 22 Sep 2026 |
| Town planner | Duplex: a few thousand to about $5,000. Townhouses and small apartments: $10,000 to $25,000 | Every project | Feasly, 14 Jun 2026 |
| Traffic and parking assessment | $2,000 to $7,000 | Larger multi-unit projects, set by council | Feasly, 7 Nov 2025 |
| Acoustic report | $2,000 to $4,000, or $5,000 to $10,000 if complex | Busy roads, apartments | Feasly, 7 Nov 2025 |
| Stormwater and drainage report | $1,500 to $5,000 | NSW councils such as Bayside want a concept plan on every DA | Feasly, 7 Nov 2025 |
| Waste management plan | $800 to $2,000 | Multi-dwelling DAs | Feasly, 7 Nov 2025 |
| Arborist report | $500 to $2,000 | Sites with trees | Feasly, 7 Nov 2025 |
| Geotechnical investigation | $2,000 to $5,000 (basic residential) | Required in NSW where there is excavation or a basement | Feasly, 7 Nov 2025 |
| QS cost report lodged with the DA | $1,000 to $3,000 | NSW, over $500,000 at Bayside | Feasly, 7 Nov 2025 |
| QS feasibility cost estimate | $2,000 to $5,000 (residential) | Before you buy or commit | Feasly, 21 Nov 2025 |
| QS initial report for the lender | $3,000 to $10,000, by project size | Before funding | Integrated Finance Group, Aug 2026 |
| QS progress inspection | $500 to $1,500 a visit | Each drawdown, during the build | Feasly, 21 Nov 2025 |
| NSW Planning Portal fee for a BASIX certificate | $5 a certificate, plus the assessor's own fee | NSW multi-unit DAs | NSW Planning Portal, 2026/27 |
| Energy rating assessor, land survey, lender valuation, lender legals | Not published in the sources we checked | Varies | Get written quotes |
Ask the architect for a fee that lists the stages it covers. Planning approval is one stage in the middle of a five-stage engagement, and engineers, the quantity surveyor and the land surveyor usually sit outside the architect's fee. Councils decide the report list. Bayside (NSW) asks for a statement of environmental effects, stormwater concept plan, arborist report and BASIX certificate on multi-unit housing, with a design review panel from three storeys. Knox (Victoria) asks for a sustainable design assessment or sustainability management plan, a levels and features plan by a licensed land surveyor, and a Metropolitan Planning Levy certificate with a multi-dwelling permit application.
Soft costs as a share of total development cost
This table adds the lines above for each project: council fee, architect at 2% to 8% of build cost, engineers at 1% to 3%, the planner, the extra reports, and three quantity surveyor jobs (DA cost report, feasibility estimate, lender report). It leaves out contingency, council infrastructure charges, finance, selling costs, land survey, valuation and legals. Total development cost (TDC) is an assumption: $2.5 million for the duplex, $6.2 million for six townhouses and $10.5 million for the apartments, each including land, build, finance and selling costs.
| Project | Pre-construction soft costs | Share of TDC | Share of build cost | Biggest line |
|---|---|---|---|---|
| Duplex, TDC $2.5m | $48,000 to $157,000 | 1.9% to 6.3% | 4.4% to 14.3% | Architect, $22,000 to $88,000 |
| Six townhouses, TDC $6.2m | $134,000 to $452,000 | 2.2% to 7.3% | 3.9% to 13.1% | Architect, $68,800 to $275,200 |
| 12 apartments, TDC $10.5m | $209,000 to $710,000 | 2.0% to 6.8% | 3.7% to 12.4% | Architect, $114,000 to $456,000 |
All figures in the table are our arithmetic on published ranges. The spread is wide because the architect percentage is wide, and a signed fee proposal removes most of it. As a cross-check, Feasly's June 2026 four-townhouse example carries $180,000 of professional fees (3.4% of its $5.33 million project cost) and $120,000 of statutory fees and infrastructure contributions. The council fee is a few thousand dollars on the duplex and under 0.2% of TDC on the apartments; the design team is where the money goes. The same costs matter to what an approved site is worth, because a buyer pays for an approval that has already absorbed them, and to subdivision costs, where the approval and survey lines repeat.
What a construction lender needs before it issues terms
A lender does not lend on a sketch. The items below come from two published lender-readiness checklists, so read them as the usual order of events rather than one lender's policy. Lenders differ, and some will give indicative terms earlier than others.
| Item | Usually needed before credit approval? | What the lender uses it for |
|---|---|---|
| Planning permit or DA | Yes. An issued approval is stronger than a lodged one, and conditions already satisfied reduce risk further | Sets what can be built and the end value |
| Feasibility with a conservative end value | Yes | Checks margin on cost, with 18% to 25% cited for a first project |
| Independent QS cost report | Yes. Described as non-negotiable with most lenders | Certifies the build cost and sets drawdown amounts |
| Fixed-price contract with a licensed builder | Yes. Cost-plus contracts are rarely accepted | Fixes the largest cost |
| Your equity and track record | Yes. A first project is asked for 25% to 35% of total project cost as equity | Shows you can carry a cost overrun |
| Lender valuation and QS initial report | After the lender decides to proceed; the borrower pays | Tests the end value and the cost to complete |
Now the honest part on appetite. Integrated Finance Group's August 2026 guide has a major bank at 65% to 75% of TDC with presales covering 100% of the debt, a non-bank senior lender at 65% to 80% with presales of 30% to 50%, and private or mezzanine money at 75% to 85% combined with presales of 0% to 30%. Feasly's page for the same period gives banks 70% to 80% of TDC and 60% to 70% of end value. Small first projects with no presales and no builder contract struggle at the banks. The soft costs themselves are almost never lent against: you pay them from your own cash before the first drawdown.
How the soft costs and the build are funded
Council fees, consultants and reports are paid before any construction facility exists, so they are equity. Lenders still count them as project cost, which means paying them lifts your contribution toward the 25% to 35% most first-time developers are asked for. The usual way to fund them is cash, or a loan secured on a home or investment property you already own. A development finance facility from a bank, a non-bank lender or a private lender then funds the build against the approval, the QS cost report and the signed contract. Private lending is typically business-purpose and not consumer regulated, and it costs more than bank debt. Ventas is a broker, not a lender, so we do not quote rates here.
Illustrative only, subject to lender assessment. Six townhouses in Brisbane, assumed total development cost of $6.2 million:
| Cost line | Amount |
|---|---|
| Land and acquisition costs (assumed) | $1,580,000 |
| Pre-construction soft costs: DA fee $10,950, architect at 4% $137,600, engineers at 1.5% $51,600, planner $15,000, reports $12,000, QS $11,000 | $238,000 |
| Construction including site works | $3,440,000 |
| Contingency at 5% of construction | $172,000 |
| Infrastructure charges, utilities, finance, selling and other (balancing figure) | $770,000 |
| Total development cost | $6,200,000 |
And how it is typically funded:
| Funding layer | Amount | What it covers | Secured on |
|---|---|---|---|
| Senior construction facility at 65% of TDC | $4,030,000 | Build and part of the finance, selling and other costs | First mortgage over the site, assignment of the building contract |
| Equity in the land | $1,580,000 | Land and acquisition | Cash, or a property-backed loan on the land or other property |
| Soft costs paid in cash | $238,000 | All pre-construction consultants and fees | Cash or a loan on existing property |
| Balance of equity before the first draw | $352,000 | Contingency and early costs | Cash or a loan on existing property |
| Total | $6,200,000 |
Equity here is $2,170,000, or 35% of TDC. To get a number from Ventas, send the site address, the DA status or lodgement date, your consultant fee proposals, the QS cost estimate or a build quote, your equity sources, and any presale plan. Start at our development application form. Finance is subject to lender assessment and approval.
- NSW Department of Planning, Housing and Infrastructure, Schedule of planning and development fees and charges 2026/27 (item 2.1, $1,000,001 to $10 million band: 30.58 fee units, $3,625, plus $1.44 per $1,000) (accessed 31 October 2026)
- City of Casey, planning permit fees 2026-2027 (fee unit $17.27; Class 13 $3,980.70, Class 14 $10,146.10, two-lot subdivision $1,537.00) (accessed 31 October 2026)
- Brisbane City Council, Schedule of Fees and Charges 2026-27 (multiple dwelling development base $9,150, $450 per unit, impact assessment $17,100; reconfiguration base $4,500 plus $900 per lot) (accessed 31 October 2026)
- Rider Levett Bucknall, Riders Digest 2026 Melbourne (walk-up units $285,000 to $585,000 a unit, townhouses $315,000 to $700,000 a unit, rates at Q4 2025 excluding land, site works and professional fees) (accessed 31 October 2026)
- Bayside Council NSW, Development Application Lodgement Checklist (QS cost report over $500,000, BASIX, stormwater concept plan, geotechnical, arborist, design review panel) (accessed 31 October 2026)
- Knox City Council, Multi-unit development (multi dwellings) planning application checklist (sustainable design assessment, surveyor levels and features plan, Metropolitan Planning Levy certificate) (accessed 31 October 2026)
- NSW Planning Portal, service fees (application for a BASIX certificate portal fee $5 for 2026/27) (accessed 31 October 2026)
- BY Projects Architecture, How much does an architect cost in Melbourne in 2026 (6 August 2026; no official fee scale) (accessed 31 October 2026)
- Feasly, Professional Fees in a Property Development Budget (22 September 2026; architect, engineer percentages, 8% to 15% overall) (accessed 31 October 2026)
- Feasly, Town planner fees for property developers (14 June 2026) (accessed 31 October 2026)
- Feasly, DA Approval in Australia developer guide (7 November 2025; report cost ranges) (accessed 31 October 2026)
- Feasly, Quantity surveyor cost estimation guide (21 November 2025; feasibility estimate and progress inspection fees) (accessed 31 October 2026)
- Feasly, Total development cost (26 June 2026; four-townhouse example) (accessed 31 October 2026)
- Feasly, Property development finance in Australia (updated 7 August 2026; bank LVR and LTC ranges) (accessed 31 October 2026)
- Integrated Finance Group, Development finance first project guide 2026 (finance broker; lender checklist, QS budget $3,000 to $10,000, equity 25% to 35%, lender-type LTC and presales, August 2026) (accessed 31 October 2026)
This is general information only and not financial, credit, or tax advice. Figures are indicative market data from the sources listed, not Ventas offers, and move with the market. Consider your own circumstances and speak to a professional. All finance is subject to lender assessment and approval.
Frequently asked questions
How much do development soft costs add up to before construction starts?
On our arithmetic from published ranges, about $48,000 to $157,000 for a duplex, $134,000 to $452,000 for six townhouses and $209,000 to $710,000 for 12 apartments. That is roughly 2% to 7% of total development cost, excluding contingency, infrastructure charges, finance and selling costs. Signed fee proposals narrow it.
How much is a DA fee for a townhouse project?
It depends on the state and the build cost. On an assumed $3.44 million build, our arithmetic gives about $7,635 in NSW, $3,980.70 in Victoria and $10,950 in Brisbane under the 2026-27 schedules. Infrastructure charges and contributions are charged separately and are usually larger.
Do I need a quantity surveyor before I apply for a DA?
Sometimes. Some NSW councils, including Bayside, require a QS estimated development cost report on works over $500,000. Lenders also want an independent QS cost report before approval. Outside NSW, councils usually ask for a cost summary, so check your council's lodgement checklist.
Can I borrow to pay the architect and consultants?
Rarely. Consultants and fees are paid before a construction facility exists, so they are normally funded from cash or a loan secured on property you already own. Lenders count them as project cost, so they count toward your equity contribution.
How much equity does a first-time developer need?
One published lender checklist says to expect 25% to 35% of total project cost as equity. Banks lend about 65% to 75% of total development cost and often want presales. Non-bank and private lenders go higher, at a higher price. Each lender sets its own limits.
Get your number from the lender panel
The figures above are indicative. Tell us what you are buying and we will come back with the real rate and repayment, usually within a day. No upfront fees and no credit check to get a quote.
Ready for the lender
Send us the site, the DA status and your cost plan. We will tell you what lenders still need and how the project is funded.
This article is general information only and not financial, credit, or tax advice. Ventas Asset Lending is a finance broker, not a lender. Approvals are subject to lender assessment. Consider your own circumstances and speak to a qualified professional, including your accountant for any tax questions.