What mezzanine finance costs in Australia
Published Australian mezzanine rates run from about 12 to 30 per cent a year, with establishment fees of 2 to 5 per cent and sometimes an exit fee or a 2 to 5 per cent profit share. On a $600,000 gap in a $6m project that is roughly $120,000 to $345,000 over 18 months.
Mezzanine finance is the layer between a senior construction loan and your own equity, and it is priced like it. It ranks second, so the lender wants a higher return for the risk of being paid after the bank. Nobody publishes an official rate, so this guide sets out what lenders, a developer and an adviser actually print, the fees and profit share on top, how far mezzanine stretches the senior limit, and what a $600,000 slice costs on a $6m project against the developer's profit. It ends with how the stack is funded.
What mezzanine finance costs in Australia
There is no official survey of mezzanine pricing in Australia. What exists is what lenders, developers and advisers publish. We opened four pages that put a number on it and set them side by side. The spread is wide, which is the first thing to know: the same $600,000 slice can cost 12 per cent a year at one end of the published range and 30 per cent at the other.
| Source | Published rate | Fees | Stretch above senior | Size and date |
|---|---|---|---|---|
| HoldenCAPITAL, mezzanine debt page | 20% to 30% p.a. (cost of funds) | 5.0% establishment, reducible on larger loans | Up to 90% of cost | $2m to $20m per project; page dated 2019 in footer |
| Roycestone Capital, mezzanine finance page | 16% to 28% p.a., interest usually capitalised | Not disclosed | 75% combined first and second mortgage; 70% to 75% when a bank lends to 65%, sometimes 80% | Minimum project profit $500,000; date Not disclosed |
| Billbergia, developer's guide to development loans | 12% to 18% p.a. | 2% to 3% establishment, 0.5% to 1.5% exit | Adds 10% to 15% on top of senior, 75% to 85% combined | Last reviewed June 2026 |
| Feasly, mezzanine guide for developers | 14% to 20% p.a.; weaker projects 22% to 24% | 2% to 4% establishment, line fee on commitment | Mezzanine 10% to 20% of total development cost | Published 24 May 2026, updated 7 August 2026 |
Read the table as indicative market data, not Ventas offers. The HoldenCAPITAL and Roycestone pages are lender-side and sit at the expensive end, with rates of 16 to 30 per cent for smaller or riskier files. Billbergia, an Australian developer, and Feasly, a feasibility software company, publish lower ranges of 12 to 20 per cent that look closer to what a sound project with an approved senior loan can expect. None of the four publishes a rate sheet you can rely on, so the lender's term sheet is the only number that counts.
Funds that lend in this space give a cross-check. Qualitas Real Estate Income Fund (ASX:QRI) reported gross income of 9.28 per cent a year across its whole loan book in April 2026, with mezzanine loans making up 5 per cent of that book and 30 per cent of its loans capitalising interest. That is a blended figure across senior and mezzanine loans, so it says more about how small the mezzanine slice is than about its price.
Fees, profit share and how far it stretches loan to cost
The interest rate is only part of the cost. Four things sit on top:
- Establishment fee. 2 to 3 per cent (Billbergia), 2 to 4 per cent (Feasly) or 5 per cent (HoldenCAPITAL). Feasly says some lenders charge it as a line fee on the committed amount, drawn or not.
- Exit fee. 0.5 to 1.5 per cent on repayment (Billbergia). Feasly says some lenders charge one but gives no figure.
- Profit share. Feasly puts the equity kicker at typically 2 to 5 per cent of project profit, sometimes triggered only above an agreed margin. HoldenCAPITAL, Roycestone and Billbergia do not state one.
- Costs passed through. Legal, valuation and, on Roycestone's page, a quantity surveyor inspection on each drawdown.
On stretch, Billbergia puts senior debt from major banks at 50 to 70 per cent of gross realisation value or total development cost, whichever is lower, and Feasly puts it at 60 to 70 per cent of total development cost. Mezzanine adds 10 to 15 per cent (Billbergia) or 10 to 20 per cent (Feasly) on top. That takes the combined loan to cost to between 75 and 85 per cent on those two pages. HoldenCAPITAL advertises up to 90 per cent of cost and Roycestone caps the combined loan at 75 per cent of value, 80 per cent in some cases. Billbergia notes the stack rarely goes above 85 per cent without preferred equity. Our development loan deposit answer and townhouse development cost guide show where the senior limits sit before mezzanine comes in.
What $600,000 of mezzanine costs against the profit
Take a $6m development where the senior lender will fund 70 per cent of cost and requires 30 per cent equity, $1.8m. The developer has $1.2m. Mezzanine fills the $600,000 gap. We assume an 18 per cent profit on cost, so $1,080,000 before mezzanine costs, and the mezzanine fully drawn for 18 months. Interest is simple and the profit share is taken on that $1,080,000. All of it is illustrative.
| Our arithmetic | Low case: 12% | Middle case: 18% | High case: 28% |
|---|---|---|---|
| Interest, 18 months fully drawn (simple) | $108,000 | $162,000 | $252,000 |
| Establishment fee | $12,000 (2%) | $18,000 (3%) | $30,000 (5%) |
| Exit fee | Nil | $6,000 (1%) | $9,000 (1.5%) |
| Profit share | Nil | $32,400 (3% of profit) | $54,000 (5% of profit) |
| Total cost of the $600,000 | $120,000 | $218,400 | $345,000 |
| Project profit after mezzanine costs (from $1,080,000) | $960,000 | $861,600 | $735,000 |
| Share of project profit the mezzanine takes | 11% | 20% | 32% |
| Return on the developer's $1.2m equity | 80% | 72% | 61% |
Across the published ranges the $600,000 costs $120,000 to $345,000 over 18 months, between 11 and 32 per cent of the project profit. Notice the return on equity. With no mezzanine the developer would need $1.8m in and make $1,080,000, a 60 per cent return. Mezzanine lets the same project go ahead on $1.2m, and even at the high case the return on equity is about the same as the no-mezzanine case. The catch is the downside. If net sales come in 10 per cent lower at $6.372m, profit before mezzanine falls from $1,080,000 to $372,000. In the middle case the mezzanine costs about $197,000 of that (the profit share shrinks too) and the developer keeps $174,840. The lender is paid before you, and a thin margin is where mezzanine stops being worth it.
Mezzanine, preferred equity and a joint venture partner
There are three ways to fill an equity gap. They rank differently, cost differently and give up different things.
| Layer or source | Published pricing | What it is |
|---|---|---|
| Holden, Roycestone, Billbergia and Feasly (mezzanine, second mortgage) | 12% to 30% p.a. | Debt, second mortgage behind the senior lender |
| Billbergia (preferred equity) | 15% to 25% fixed | Equity instrument, plus a share of profit on completion (percentage Not disclosed) |
| Feasly (preferred equity) | 10% to 18%, varies by structure | Equity instrument, no mortgage |
| Billbergia and Feasly (senior bank or non-bank construction debt, for scale) | 7% to 9% (Billbergia, major banks, 2026); 7% to 11% (Feasly) | First mortgage |
| Knight Frank (credit funds, all real estate debt) | 3% to 6.5% above the RBA cash rate | Fund return target, not a mezzanine rate |
| MaxCap Group, quoted by Development Ready (private real estate credit) | 5% to 8% above the RBA cash rate | Fund return, not a mezzanine rate |
Mezzanine is debt secured by a second mortgage, with a priority deed. You keep control and, apart from any kicker, the upside. Preferred equity is not a mortgage, so it needs no second mortgage or subordination deed. The Urban Developer reports that banks are more willing to accept it because they are reluctant to consent to second mortgages on construction projects. It usually carries a fixed return, and some deals add a share of profit. Feasly's worked example puts a 12 per cent coupon with a 10 per cent kicker on $1 million of hard preferred equity, which is one example, not a market rate.
A joint venture partner contributes equity for a share of profit rather than a coupon. We found no published rate range for joint ventures, so we will not make one up. The split is negotiated. Feasly's preferred equity waterfall example moves from 80/20 in the investor's favour to 70/30 or 60/40 in the sponsor's favour as returns pass about 18 to 20 per cent IRR, but that is an illustration of how a waterfall steps, not a benchmark. What is true of every structure is that a partner who shares profit costs more when the project goes well, while a lender with a fixed coupon costs more when it goes badly.
Priority deeds, lender appetite and what makes a deal fundable
Be straight about appetite: mezzanine is a small, selective market. Qualitas holds only 5 per cent of its fund in mezzanine loans. In 2021 the joint managing director of Stamford Capital told Broker News that he had not seen bank-provided mezzanine in three or four years, and Mortgage Business ran a 2018 piece headlined that bank mezz loans were a thing of the past. Today the money comes mostly from non-bank and private lenders. IFR, citing ASIC, puts Australian private credit at about A$200bn with roughly half in real estate. ASIC's Report 820 (November 2025) flagged real estate construction and development lending as drawing the most concern, so lenders are checking valuations and borrower fees harder.
What lenders ask for, according to the pages above:
- An approved project and senior debt lined up. Roycestone wants a copy of the construction loan facility and says mezzanine must sit behind a bank or second-tier lender.
- Size and margin. Feasly puts the minimum project at about $2m to $3m of total development cost, with most mezzanine lenders preferring $5m or more, and lender models wanting roughly 18 to 22 per cent profit on cost. Roycestone states a $500,000 minimum project profit.
- Real equity from you. Feasly says mezzanine lenders want at least 10 to 15 per cent of total development cost in genuine sponsor equity.
- A deed of priority. Feasly lists a cap on the senior facility, standstill periods, cure rights, buy-out rights and notification duties. Personal guarantees, it says, are almost universal.
- The senior lender's consent. Without it there is no second mortgage.
ASIC says loans to companies are outside the credit legislation, and a loan to a natural person to buy or build residential property for investment is caught. Most developers borrow through a company or trust, so these facilities are usually business purpose and not consumer regulated, but check the borrower structure. Ask your accountant how mezzanine interest and any profit share are treated for tax.
Financing the equity gap with mezzanine
A development stack has a senior lender at the front, mezzanine behind it, then your equity. Banks lend roughly 60 to 70 per cent of cost, non-bank lenders go higher, and mezzanine or preferred equity covers part of what is left. Ventas is a broker, not a lender, so we do not quote rates or promise approval. Here is how the example in this guide is built.
Illustrative only, subject to lender assessment. A $6m project:
| Item | Amount |
|---|---|
| Land and acquisition costs | $2,000,000 |
| Construction | $3,100,000 |
| Professional fees and approvals | $300,000 |
| Senior interest and finance costs | $350,000 |
| Selling and holding costs | $250,000 |
| Total development cost | $6,000,000 |
| Net sales (assumed 18% profit on cost) | $7,080,000 |
And how it is typically funded:
| Funding layer | Amount | Secured on | Typically from |
|---|---|---|---|
| Senior construction loan | $4,200,000 (70%) | First mortgage, QS-certified drawdowns, presales as the senior lender requires | Bank or non-bank |
| Mezzanine loan | $600,000 (10%) | Second mortgage behind the senior, deed of priority | Non-bank or private |
| Developer equity | $1,200,000 (20%) | Land at valuation plus cash | You |
| Total | $6,000,000 | Combined loan to cost 80% |
The senior lender must agree to the mezzanine in writing, and the combined loan to cost of 80 per cent has to fit both lenders' credit policy. What makes it fundable is an approved project, a senior offer in hand, real equity, a margin that survives a fall in sales, and a clear exit by settlements. Where a senior lender will not consent to a second mortgage, preferred equity is the usual alternative. To get a number, send Ventas the feasibility, the senior offer, the equity you have in and the gap. Start with mezzanine finance and see development finance. Finance is subject to lender assessment and approval.
- HoldenCAPITAL, mezzanine debt page (loan range $2m to $20m, up to 90% of cost, cost of funds 20% to 30% p.a., 5.0% establishment fee) (accessed 30 October 2026)
- Roycestone Capital, mezzanine finance page (16% to 28% p.a., 75% combined LVR, minimum project profit $500,000, application requirements) (accessed 30 October 2026)
- Billbergia, A Developer's Guide to Property Development Loans in Australia (published 25 April 2025, reviewed June 2026: mezzanine 12% to 18%, fees, senior and preferred equity ranges) (accessed 30 October 2026)
- Feasly, Mezzanine Finance for Property Development in Australia (published 24 May 2026, updated 7 August 2026: coupons, fees, equity kicker, deed terms, lender criteria) (accessed 30 October 2026)
- Feasly, Equity Partners and Preferred Equity for Property Development (published 7 May 2026, updated 7 August 2026: preferred equity pricing and waterfall example) (accessed 30 October 2026)
- Qualitas Real Estate Income Fund (ASX:QRI), Performance Update April 2026 (mezzanine 5% of portfolio, gross income 9.28% p.a., 30% of loans capitalising interest) (accessed 30 October 2026)
- ASIC, Report 820 Private credit surveillance: retail and wholesale funds (November 2025: real estate development lending concerns, borrower fees, 'as if complete' LVR) (accessed 30 October 2026)
- ASIC, FAQs: does the credit legislation apply (loans to companies, residential investment property) (accessed 30 October 2026)
- ASIC, Regulatory Guide 45 Mortgage schemes: improving disclosure for retail investors (issued 5 March 2026) (accessed 30 October 2026)
- Knight Frank, Australia's private credit market set for sustained growth as traditional lending tightens (6 October 2025: credit funds seek 3% to 6.5% above the RBA cash rate) (accessed 30 October 2026)
- Development Ready, private credit surge signals shift in commercial real estate finance (27 June 2025: CBRE private credit share of residential development debt, MaxCap 5% to 8% over cash rate) (accessed 30 October 2026)
- IFR, Aussie real estate market faces private credit test (IFR 2640, 4 to 10 July 2026: A$200bn market, about half real estate, per ASIC) (accessed 30 October 2026)
- The Urban Developer, How to use preferential equity to preserve your development capital (preferred equity needs no second mortgage or subordination deed) (accessed 30 October 2026)
- Broker News, Mezzanine finance on the comeback in commercial property (8 April 2021, Stamford Capital on bank mezzanine disappearing) (accessed 30 October 2026)
- Mortgage Business, Permanently gone: bank mezz loans a thing of the past (21 June 2018, Qualitas) (accessed 30 October 2026)
This is general information only and not financial, credit, or tax advice. Figures are indicative market data from the sources listed, not Ventas offers, and move with the market. Consider your own circumstances and speak to a professional. All finance is subject to lender assessment and approval.
Frequently asked questions
What interest rate does mezzanine finance charge in Australia?
Published figures run from about 12 to 30 per cent a year. Billbergia lists 12 to 18, Feasly 14 to 20, Roycestone 16 to 28 and HoldenCAPITAL 20 to 30. There is no official survey, so treat these as indicative and check the lender's term sheet.
What fees come with mezzanine finance?
Establishment fees are published at 2 to 5 per cent of the facility, some lenders add an exit fee of 0.5 to 1.5 per cent, and Feasly says a profit share of 2 to 5 per cent is typical. Legal, valuation and drawdown inspection costs are usually passed through.
How far does mezzanine stretch loan to cost?
Published pages put senior debt at 60 to 70 per cent of cost and mezzanine adding 10 to 20 per cent, so 75 to 85 per cent combined. HoldenCAPITAL advertises up to 90 per cent. Billbergia says the stack rarely passes 85 per cent without preferred equity.
Is mezzanine cheaper than preferred equity or a joint venture?
Published mezzanine ranges (12 to 30 per cent) overlap preferred equity (10 to 25 per cent). A joint venture takes a share of profit instead of a coupon and has no published range. The cheapest depends on how well the project performs, so run the feasibility both ways.
Does the senior lender have to agree to mezzanine?
Yes. Mezzanine takes a second mortgage, so the senior lender signs a deed of priority covering things like standstill periods and cure rights. Banks can be reluctant to agree, which is why preferred equity, which needs no second mortgage, is sometimes used instead.
Get your number from the lender panel
The figures above are indicative. Tell us what you are buying and we will come back with the real rate and repayment, usually within a day. No upfront fees and no credit check to get a quote.
Closing the equity gap
Send us the feasibility, the senior debt offer and the equity you have in. We will show you how the gap can be funded and what it costs.
This article is general information only and not financial, credit, or tax advice. Ventas Asset Lending is a finance broker, not a lender. Approvals are subject to lender assessment. Consider your own circumstances and speak to a qualified professional, including your accountant for any tax questions.