What it costs to develop an apartment building in Australia

Ventas Asset Lending  |  Reviewed by Caleb Morehu  |  Updated 23 November 2026

Building apartments up to 10 storeys costs about $3,500 to $5,700 per square metre in Australian capitals (RLB, fourth quarter 2025, excluding GST and parking), roughly $424,000 to $690,000 an apartment. Add land, basement parking, fees and finance and a worked 14-unit Brisbane project totals about $16.4 million, or $1.17 million an apartment.

$3,500 to $5,700per m2 to build apartments up to 10 storeys, by city (RLB, Q4 2025)
$55,000 to $110,000per basement space in Sydney (RLB)
$16.4mworked total for 14 apartments, about $1.17m each (our arithmetic)
About 35%equity in the worked example, our arithmetic

A small apartment building costs far more than its build rate suggests. The published rate covers the structure and fit-out only. Basement parking, council charges, consultants, contingency, finance and selling costs sit on top, and together they often add 30 to 50 per cent to the build contract. This guide sets out what RLB publishes for apartments by city, what basement parking and soft costs add, a worked total for a 14-unit project, and how development lenders view a first or second apartment project, for developers stepping up from townhouses, builders developing their own sites and landowners partnering on a project.

What apartments cost to build by city

Rider Levett Bucknall (RLB) publishes the benchmark rates that quantity surveyors and lenders use. The table shows RLB's fourth quarter 2025 rates for 60 to 70 m2 apartments in buildings up to 10 storeys, which covers every small and mid-size project in this guide. Rates are per square metre of gross floor area (GFA), exclude GST and exclude car parking. The last column is our arithmetic: the rate applied to 121 m2 of GFA per apartment, the figure used in the worked example below (about 85 m2 of internal area plus a share of stairs, lifts, corridors and walls). Figures are indicative market data and not Ventas offers.

CityRLB, up to 10 storeys, $/m2 GFAMid-rise, 10 to 20 storeys, $/m2Build per apartment at 121 m2 GFA, our arithmetic
Sydney$4,200 to $5,700$4,700 to $6,200about $508,000 to $690,000
Melbourne$4,300 to $5,200$4,300 to $5,700about $520,000 to $629,000
Brisbane$4,250 to $5,000$5,000 to $6,000about $514,000 to $605,000
Perth$4,100 to $5,500$4,350 to $5,800about $496,000 to $666,000
Adelaide$3,700 to $4,550$4,150 to $5,200about $448,000 to $551,000
Canberra$3,750 to $5,600$4,000 to $6,100about $454,000 to $678,000
Darwin$3,500 to $4,500$3,600 to $4,700about $424,000 to $545,000

Three other published price points frame the table. Queensland's average construction cost per apartment rose 14 per cent in the 2025 financial year to $713,000 (The Urban Developer, 16 October 2025, which does not name the source of the figure). Urbis reports new apartments averaging nearly $18,000 per m2 nationally in the fourth quarter of 2025, up 16 per cent on the quarter, which is a sale price and not a cost. And Feasly says the build contract is often 50 to 65 per cent of total development cost, with demolition, external works, infrastructure charges, professional fees, contingency and finance adding 30 to 50 per cent on top of it for a multi-unit project.

A 10 to 20 unit project is usually three to six storeys, so the first column applies; the second shows how cost steps up with height. For other building types, see our construction cost per square metre guide.

Basement parking

Parking is priced separately from the building rate, and for a small apartment block it is often the largest single add-on. RLB prices Sydney basement parking at $58,000 to $110,000 per space in the CBD and $55,000 to $100,000 per space outside it, based on about 30 m2 per car. RLB does not publish a per-space figure for the other cities in the sources we checked, so a Brisbane, Melbourne or Perth project needs a quantity surveyor's own number. Excavation, shoring, groundwater and rock decide where in the range a site lands.

A 14-apartment block with 18 car spaces at the bottom of Sydney's non-CBD range is about $990,000 of basement before the building starts. At-grade parking is cheaper where a council allows it, but it uses land that could carry more apartments.

Soft costs, charges and duty

Soft costs are everything that is not the land, the building or the parking. They are paid early, mostly before any construction loan exists, so they are largely equity. The table below uses published ranges and is read with our development soft costs guide, which has the consultant and council fee schedules in full.

CostPublished figureSource
Professional fees (architect, engineers, planner, certifier, QS, project manager)8% to 15% of construction cost, wide because sources use different denominatorsFeasly, September 2026 (as quoted in our soft costs guide)
Queensland infrastructure charges, 1 to 2 bedroom dwelling$27,163.80 per dwelling at Toowoomba, 3 or more bedrooms $38,029.25 (from 1 September 2025). The state sets the cap councils can chargeToowoomba Regional Council
Brisbane infrastructure chargesPer-dwelling amounts are in Brisbane Infrastructure Charges Resolution (No. 15) 2026, in force from 1 July 2026, and are indexed. Council gives estimates on request. Indexation applies at payment using the Producer Price Index, up to the state capBrisbane City Council
City of Sydney contributionsThe council's page lists its plans (Central Sydney 2020 and Ultimo Pyrmont 2023 under section 7.12, the 2015 plan under section 7.11) but shows no dollar rates, so read the plan itself. Secondary and indicative only: Feasly cites $15,458 to $20,000 a dwelling under section 7.11 as of December 2024City of Sydney; Feasly, 22 November 2025
Everything on top of the build contract30% to 50% extra for a multi-unit project once the items above, demolition, external works, contingency and finance are includedFeasly, 7 July 2026

Two practical points. Charges are set per dwelling, so a mix of one and two-bedroom apartments carries a lower charge than three-bedroom units in Queensland, and councils in some states discount small dwellings in identified areas. And transfer duty on the land is a real cost: in Queensland a $4.2 million site pays $38,025 plus $5.75 per $100 over $1 million, which is $222,025 (our arithmetic on the Queensland Revenue Office schedule). Duty differs in every state, so price it for your own site.

Worked example: 14 apartments in Brisbane

The numbers below are one illustrative project, not a quote. It is 14 apartments averaging 85 m2 internal on a 1,800 m2 middle-ring Brisbane site, three to four storeys over one level of basement with 18 car spaces, built on a fixed-price contract over about 18 months. Everything is excluding GST. Build cost uses the middle of RLB's Brisbane range, $4,600 per m2, on 1,700 m2 of GFA. Land, parking, infrastructure charges, finance and selling costs are our assumptions.

Illustrative only, subject to lender assessment.

Cost lineAmountBasis
Land, 1,800 m2$4,200,000Assumption, $300,000 an apartment
Transfer duty and acquisition legals$247,000Duty $222,025 on the QRO schedule, legals $25,000, our arithmetic
Building, 1,700 m2 at $4,600$7,820,000Fixed price contract, RLB Brisbane range
Basement parking, 18 spaces$990,000Assumption at $55,000 a space, the low end of RLB's Sydney non-CBD range
Professional fees$793,0009% of building and parking, inside Feasly's 8% to 15%
Council fee and infrastructure charges$365,000Assumption: $25,000 a dwelling plus about $15,000 of application fee
Contingency$440,0005% of building and parking, inside Feasly's 5 to 10% for a contracted project
Finance, establishment and holding$1,150,000Assumption: about $10.65m facility, about half drawn on average over 18 months at about 10.5%, plus fees and approval-period holding
Selling and settlement costs$392,000Assumption, $28,000 an apartment
Total development cost (TDC)$16,397,000About $1,171,000 an apartment

Building and parking are 54 per cent of TDC, inside Feasly's 50 to 65 per cent. Everything other than land, duty and the build adds about 36 per cent on top of the build and parking, inside Feasly's 30 to 50 per cent. The break-even sale price is $1,171,000 an apartment excluding GST, or about $13,800 per m2 of internal area. A 15 per cent margin on cost needs about $1,347,000 an apartment, or $15,800 per m2 (our arithmetic). Compare that with Urbis's national average for new apartments of nearly $18,000 per m2 (the report does not say whether that includes GST), and with what comparable stock actually sells for in your suburb. The gap between the two is the whole feasibility.

For unit-for-unit comparisons at a smaller scale, our townhouse development cost guide uses the same method. If an apartment project completes and some stock does not sell, residual stock pricing shows what the exit looks like.

Who builds small apartment projects

Most 10 to 20 unit projects are run by one of three people. Townhouse developers stepping up keep the same consultants and a similar presales approach but meet new costs: a lift or stair core, a basement, fire engineering and a longer build. Builders developing their own sites know the build price, but a lender still wants an independent QS and a builder contract that is not simply the developer's own company, and ANZ's Daniel Gradwell has said banks now treat developer-builder projects much like those with a third-party builder while builder insolvencies remain a key lending challenge (The Urban Developer, October 2025). Landowners partnering with a developer usually contribute the land as equity, which lowers the cash needed, but the lender will look at the land's value and the terms of the joint venture. Demand for the product is there: the ABS recorded 17,948 dwellings approved nationally in September 2026 (seasonally adjusted), 6,579 of them private dwellings other than houses. Whichever route, the sponsor has to show the margin and an ability to carry an overrun.

How an apartment development is funded

Lenders are cautious about small apartment projects. The reasons are single-asset risk, thin presale markets and builder insolvencies. Feasly's private lender page (updated 7 August 2026, indicative) says many major banks effectively will not look at projects below about $10 million of total development cost, and that private lenders routinely fund smaller deals. Switchboard Finance (21 August 2026) says facilities for two to six dwellings are often written without presales, but from five dwellings a lender assesses a development with a residual margin test, so a 14-unit block is assessed that way; Feasly says senior lenders usually require presales on apartments. Feasly gives the ranges below.

Lender typeLoan to costLoan to valuePresalesIndicative senior rate
Bank construction60% to 70%60% to 65%Substantial, qualifying presalesNot published on that page
Non-bank senior70% to 80%65% to 70%, up to 75%0% to 50%8.5% to 13.0% a year, by lender tier
Stretch senior80% to 85%70% to 75%VariableHigher, not separately published
Private short-term seniorCase by caseCase by caseMay accept none with a strong exit10.75% to 14.0%
Mezzanine, second mortgageFills the gap, often 10% to 20% of TDCn/an/a14% to 22%, plus establishment fees of 2% to 4%

Ventas is a broker, not a lender, so we do not quote rates and these are not offers. Private lending is typically business-purpose and not consumer regulated. A bank senior loan is cheaper but wants presales and a larger project. A non-bank lender asks for less presale cover and charges more. Private and mezzanine money is the most expensive and the most flexible. A construction facility funds the build only after the land, soft costs and early charges are paid in equity.

Illustrative only, subject to lender assessment. The same $16,397,000 project funded as follows:

Funding layerAmountWhat it coversSecured on
Senior construction facility, about 65% of TDC$10,650,000Build, parking, fees, finance and part of the selling costsFirst mortgage over the site, assignment of the building contract
Equity in the land and duty$4,447,000Land, duty and acquisition legalsCash, or a loan on property you already own
Equity for soft costs and early costs$1,300,000Consultants, charges, contingency and costs before the first drawdownCash, or a property-backed loan
Total$16,397,000

Equity is $5,747,000, or 35 per cent of TDC. That is well above the 10 to 15 per cent minimum that Feasly's mezzanine page cites, because a senior lender at 65 per cent leaves the rest to you, and first-time developers are typically asked to contribute more (Switchboard Finance, August 2026). Many projects therefore need a second source: a loan secured on a home or other property, a landowner contributing the site, or mezzanine money. Our deposit for a development loan page explains how lenders count equity.

What makes an apartment deal fundable:

To get a number from Ventas, send the site address and approval status, the unit mix and areas, the builder's quote or QS estimate, your equity and its source, and any presale plan. Start at development finance. Finance is subject to lender assessment and approval.

Sources

This is general information only and not financial, credit, or tax advice. Figures are indicative market data from the sources listed, not Ventas offers, and move with the market. Consider your own circumstances and speak to a professional. All finance is subject to lender assessment and approval.

Frequently asked questions

How much does it cost to build apartments in Australia?

RLB's fourth quarter 2025 rates for apartments up to 10 storeys run from $3,500 per m2 in Darwin to $5,700 in Sydney, excluding GST and parking. At 121 m2 of gross floor area an apartment, that is about $424,000 to $690,000 before basement parking and soft costs.

How much does a 14 unit apartment development cost?

Our worked example comes to about $16.4 million, or $1.17 million an apartment, for a Brisbane site with a basement. It includes land, duty, the build, parking, fees, charges, finance and selling costs. Your total depends on the site, the city and the car parking needed.

How much does basement parking cost per space?

RLB prices Sydney basement parking at $58,000 to $110,000 per space in the CBD and $55,000 to $100,000 outside it, at about 30 m2 a car. It has no published per-space figure for the other capitals in the sources we checked, so ask a quantity surveyor.

How much equity do I need for an apartment development?

In our example it is about 35 per cent of total development cost, near $5.7 million on a $16.4 million project. Banks and non-banks differ, and the figure rises if presales are low or the lender wants a cost buffer. Land held already counts toward it.

Can I get a loan for a small apartment development?

Often, but not from every lender. Many major banks effectively will not look at projects under about $10 million of total development cost, while non-bank and private lenders routinely fund smaller deals. Approval depends on the approval, the builder contract, presales, equity and your track record.

CM
Reviewed by Caleb Morehu, Co-founder, Ventas Asset Lending. Caleb structures asset, property-backed and development finance and negotiates directly with lenders. Every figure on this page is checked against what lenders are actually approving. About Ventas.

Get your number from the lender panel

The figures above are indicative. Tell us what you are buying and we will come back with the real rate and repayment, usually within a day. No upfront fees and no credit check to get a quote.

No upfront fees. We are paid by the lender at settlement.

Working up an apartment project?

Send us the site, the yield and your feasibility. We will come back with how development lenders will look at the presales, the equity and the build, and a structure, usually within a day.

This article is general information only and not financial, credit, or tax advice. Ventas Asset Lending is a finance broker, not a lender. Approvals are subject to lender assessment. Consider your own circumstances and speak to a qualified professional, including your accountant for any tax questions.